Building a Garage
Saturday, December 13, 2008
All 4 walls now up.
All four walls are now framed and up. 2 20"x20" windows on the south wall. 9'wx7h garage door. Used 17' LVL on front front wall.
Tuesday, December 2, 2008
First wall up
Forgot to add the picture of the cement truck and pumper truck. Figured I would get rid of the driveway settling problem where the driveway meets the garage floor. Had them install a 6' apron.
Sunday, November 30, 2008
Framing Started
Lifting up the first wall.
1 row of concrete block around perimeter of slab.
Thursday, November 27, 2008
Dirt work continued...
Day 1
The dirt work begins. Diesel bobcat had its work cut out. You can see where I lowered the lawnmower blade to outline the size/location. 20'x20'.